S125-W8 Connector over Grossmont Center Drive
GoodSan Diego County, California · 11-SD-125-R15.47-LMSA · Structure no. 57 0975F
- Built
- 1993
- 32 years old
- Condition
- Good
- inspected August 2024
- Type
- Box Beam or Girders - Multiple
- Prestressed Concrete
- Length
- 156 ft
- 1 main span
- Daily traffic
- 5,700
- 2020 count
- Owner
- State
- State Highway Agency
About this bridge
S125-W8 Connector over Grossmont Center Drive is a prestressed concrete box beam or girders - multiple carrying S125-W8 Connector over Grossmont Center Drive in San Diego County, California. It was built in 1993, so it is 32 years old, younger than the California average of 54.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 5,700 vehicles a day, roughly 2% of them trucks, projected to reach 10,760 by 2042. The structure is 156 ft (47.5 m) long and 38 ft wide. If it were closed, the detour would be 1.2 mi (2 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was S125-W8 Connector over Grossmont Center Drive built?
It was built in 1993, making it 32 years old in 2025.
What condition is S125-W8 Connector over Grossmont Center Drive in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in August 2024.
How much traffic does S125-W8 Connector over Grossmont Center Drive carry?
About 5,700 vehicles per day (2020 count), of which roughly 2% are trucks.
How long is S125-W8 Connector over Grossmont Center Drive?
The structure is 156 ft (47.5 m) long with a longest span of 154 ft (46.9 m) and a deck 38 ft wide.
Who owns S125-W8 Connector over Grossmont Center Drive?
It is owned by the State Highway Agency.