Grant Line RD over East Branch Laguna Creek
GoodSacramento County, California · 0.4 MI SW Calvine RD · Structure no. 24C0018
- Built
- 1939
- 86 years old, rebuilt 1990
- Condition
- Good
- inspected April 2023
- Type
- Slab
- Concrete Continuous
- Length
- 82 ft
- 5 main spans
- Daily traffic
- 14,664
- 2014 count
- Owner
- City
- City or Municipal Highway Agency
About this bridge
Grant Line RD over East Branch Laguna Creek is a concrete continuous slab carrying Grant Line RD over East Branch Laguna Creek in Sacramento County, California. It was built in 1939 and reconstructed in 1990, so it is 86 years old, older than the California average of 54.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 14,664 vehicles a day, roughly 10% of them trucks, projected to reach 23,751 by 2043. The structure is 82 ft (25 m) long and 43 ft wide. If it were closed, the detour would be 1.2 mi (2 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
| Channel and channel protection | 6 Satisfactory | Structural elements show some minor deterioration. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Grant Line RD over East Branch Laguna Creek built?
It was built in 1939, making it 86 years old in 2025. It was reconstructed in 1990.
What condition is Grant Line RD over East Branch Laguna Creek in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in April 2023.
How much traffic does Grant Line RD over East Branch Laguna Creek carry?
About 14,664 vehicles per day (2014 count), of which roughly 10% are trucks.
How long is Grant Line RD over East Branch Laguna Creek?
The structure is 82 ft (25 m) long with a longest span of 22 ft (6.7 m) and a deck 43 ft wide.
Who owns Grant Line RD over East Branch Laguna Creek?
It is owned by the City or Municipal Highway Agency.