Avenue 15 1/5 over Future High Speed Rail
GoodMadera County, California · Near Intersect of Road 29 · Structure no. 41C0231
- Built
- 2022
- 3 years old
- Condition
- Good
- inspected March 2023
- Type
- Stringer/Multi-beam or Girder
- Prestressed Concrete Continuous
- Length
- 469 ft
- 4 main spans
- Daily traffic
- 1,000
- 2022 count
- Owner
- State
- Other State Agency
About this bridge
Avenue 15 1/5 over Future High Speed Rail is a prestressed concrete continuous stringer/multi-beam or girder carrying Avenue 15 1/5 over Future High Speed Rail in Madera County, California. It was built in 2022, so it is 3 years old, younger than the California average of 54.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 1,000 vehicles a day, roughly 3% of them trucks, projected to reach 1,300 by 2042. The structure is 469 ft (142.8 m) long and 43 ft wide.
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Avenue 15 1/5 over Future High Speed Rail built?
It was built in 2022, making it 3 years old in 2025.
What condition is Avenue 15 1/5 over Future High Speed Rail in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in March 2023.
How much traffic does Avenue 15 1/5 over Future High Speed Rail carry?
About 1,000 vehicles per day (2022 count), of which roughly 3% are trucks.
How long is Avenue 15 1/5 over Future High Speed Rail?
The structure is 469 ft (142.8 m) long with a longest span of 147 ft (44.7 m) and a deck 43 ft wide.
Who owns Avenue 15 1/5 over Future High Speed Rail?
It is owned by the Other State Agency.