N Fruit Ave over Herndon Canal
FairFresno County, California · 0.22 MI N Dakota Ave · Structure no. 42C0207
- Built
- 1961
- 64 years old, rebuilt 1981
- Condition
- Fair
- inspected December 2024
- Type
- Slab
- Concrete Continuous
- Length
- 56 ft
- 2 main spans
- Daily traffic
- 10,846
- 2007 count
- Owner
- City
- City or Municipal Highway Agency
About this bridge
N Fruit Ave over Herndon Canal is a concrete continuous slab carrying N Fruit Ave over Herndon Canal in Fresno County, California. It was built in 1961 and reconstructed in 1981, so it is 64 years old, older than the California average of 54.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 5 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
It carries about 10,846 vehicles a day, roughly 2% of them trucks, projected to reach 15,317 by 2042. The structure is 56 ft (17.1 m) long and 79 ft wide. If it were closed, the detour would be 1.2 mi (2 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Superstructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Substructure | 7 Good | Some minor problems. |
| Channel and channel protection | 8 Very Good | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was N Fruit Ave over Herndon Canal built?
It was built in 1961, making it 64 years old in 2025. It was reconstructed in 1981.
What condition is N Fruit Ave over Herndon Canal in?
The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in December 2024.
How much traffic does N Fruit Ave over Herndon Canal carry?
About 10,846 vehicles per day (2007 count), of which roughly 2% are trucks.
How long is N Fruit Ave over Herndon Canal?
The structure is 56 ft (17.1 m) long with a longest span of 27 ft (8.2 m) and a deck 79 ft wide.
Who owns N Fruit Ave over Herndon Canal?
It is owned by the City or Municipal Highway Agency.