Hawes Road over Powerline Floodway Chnl
GoodMaricopa County, Arizona · 0.1 Mile S/Ray Road · Structure no. 11641
- Built
- 2020
- 5 years old
- Condition
- Good
- inspected February 2023
- Type
- Stringer/Multi-beam or Girder
- Prestressed Concrete
- Length
- 69 ft
- 1 main span
- Daily traffic
- 4,200
- 2022 count
- Owner
- City
- City or Municipal Highway Agency
About this bridge
Hawes Road over Powerline Floodway Chnl is a prestressed concrete stringer/multi-beam or girder carrying Hawes Road over Powerline Floodway Chnl in Maricopa County, Arizona. It was built in 2020, so it is 5 years old, younger than the Arizona average of 47.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 8 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 4,200 vehicles a day, roughly 5% of them trucks, projected to reach 4,210 by 2042. The structure is 69 ft (21 m) long and 88 ft wide. If it were closed, the detour would be 5 mi (8 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 8 Very Good | No problems noted. |
| Superstructure | 8 Very Good | No problems noted. |
| Substructure | 8 Very Good | No problems noted. |
| Channel and channel protection | 9 Excellent | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Hawes Road over Powerline Floodway Chnl built?
It was built in 2020, making it 5 years old in 2025.
What condition is Hawes Road over Powerline Floodway Chnl in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in February 2023.
How much traffic does Hawes Road over Powerline Floodway Chnl carry?
About 4,200 vehicles per day (2022 count), of which roughly 5% are trucks.
How long is Hawes Road over Powerline Floodway Chnl?
The structure is 69 ft (21 m) long with a longest span of 65 ft (19.8 m) and a deck 88 ft wide.
Who owns Hawes Road over Powerline Floodway Chnl?
It is owned by the City or Municipal Highway Agency.