_co RD 1021 over _nf Southern Railroad
GoodPosted for loadChambers County, Alabama · _2 Mi. E. Waverly · Structure no. 021685
- Built
- 2021
- 4 years old
- Condition
- Good
- inspected February 2025
- Type
- Stringer/Multi-beam or Girder
- Wood or Timber
- Length
- 106 ft
- 1 main span
- Daily traffic
- 130
- 2009 count
- Owner
- County
- County Highway Agency
About this bridge
_co RD 1021 over _nf Southern Railroad is a wood or timber stringer/multi-beam or girder carrying _co RD 1021 over _nf Southern Railroad in Chambers County, Alabama. It was built in 2021, so it is 4 years old, younger than the Alabama average of 51.1 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. Its operating status is: posted for load restriction.
It carries about 130 vehicles a day, roughly 6% of them trucks, projected to reach 2,039 by 2039. The structure is 106 ft (32.3 m) long and 20 ft wide. If it were closed, the detour would be 6.2 mi (10 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 8 Very Good | No problems noted. |
| Substructure | 8 Very Good | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was _co RD 1021 over _nf Southern Railroad built?
It was built in 2021, making it 4 years old in 2025.
What condition is _co RD 1021 over _nf Southern Railroad in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in February 2025.
How much traffic does _co RD 1021 over _nf Southern Railroad carry?
About 130 vehicles per day (2009 count), of which roughly 6% are trucks.
How long is _co RD 1021 over _nf Southern Railroad?
The structure is 106 ft (32.3 m) long with a longest span of 17 ft (5.2 m) and a deck 20 ft wide.
Who owns _co RD 1021 over _nf Southern Railroad?
It is owned by the County Highway Agency.