US Bridges

Te Cnty RD 3 over Fish Creek

Good

Teton County, Wyoming · Wilson Square Road · Structure no. KKW

Built
1995
30 years old
Condition
Good
inspected August 2024
Type
Slab
Wood or Timber
Length
65 ft
3 main spans
Daily traffic
1,042
2024 count
Owner
County
County Highway Agency

About this bridge

Te Cnty RD 3 over Fish Creek is a wood or timber slab carrying Te Cnty RD 3 over Fish Creek in Teton County, Wyoming. It was built in 1995, so it is 30 years old, younger than the Wyoming average of 48.4 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 1,042 vehicles a day, roughly 13% of them trucks, projected to reach 1,459 by 2043. The structure is 65 ft (19.7 m) long and 32 ft wide.

CarriesTe Cnty RD 3
CrossesFish Creek
LocationWilson Square Road
RouteCounty Highway 13
StateWyoming
Coordinates43.49972, -110.87042
Functional classRural Minor Collector

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck8 Very GoodNo problems noted.
Superstructure8 Very GoodNo problems noted.
Substructure7 GoodSome minor problems.
Channel and channel protection8 Very GoodNo problems noted.
Last inspectionAugust 2024
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourFoundations stable; scour above top of footing
Structural evaluation7: Better than present minimum criteria
Deck geometry5: Somewhat better than minimum adequacy to tolerate being left in place as is
Waterway adequacy8: Equal to present desirable criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating59 US tons
Inventory rating42 US tons

Structure

Structure typeSlab
MaterialWood or Timber
DeckWood or timber
Main spans3
Design loadHS 20
Structure length65 ft (19.7 m)
Longest span21 ft (6.4 m)
Deck width32 ft (9.8 m)
Roadway width30 ft (9.1 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic1,042 (2024)
Projected traffic1,459 by 2043
Trucks13%
Lanes on structure2
Traffic directionTwo-way traffic
CarriesHighway
CrossesWaterway
Detour if closed—
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerCounty Highway Agency
Maintained byCounty Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedOther structural work, including hydraulic replacements
Estimated improvement cost$4,000
NavigationNo navigation control on waterway

Frequently asked questions

When was Te Cnty RD 3 over Fish Creek built?

It was built in 1995, making it 30 years old in 2025.

What condition is Te Cnty RD 3 over Fish Creek in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in August 2024.

How much traffic does Te Cnty RD 3 over Fish Creek carry?

About 1,042 vehicles per day (2024 count), of which roughly 13% are trucks.

How long is Te Cnty RD 3 over Fish Creek?

The structure is 65 ft (19.7 m) long with a longest span of 21 ft (6.4 m) and a deck 32 ft wide.

Who owns Te Cnty RD 3 over Fish Creek?

It is owned by the County Highway Agency.