US Bridges

Lrd Highland DR over Artus Creek

Good

Marathon County, Wisconsin · 1.1M E JCT Sth 107 · Structure no. B37047000000000

Built
2023
2 years old
Condition
Good
inspected October 2023
Type
Slab
Concrete
Length
76 ft
2 main spans
Daily traffic
110
2023 count
Owner
Town / Township
Town or Township Highway Agency

About this bridge

Lrd Highland DR over Artus Creek is a concrete slab carrying Lrd Highland DR over Artus Creek in Marathon County, Wisconsin. It was built in 2023, so it is 2 years old, younger than the Wisconsin average of 40.3 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 9 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 110 vehicles a day, roughly 5% of them trucks, projected to reach 150 by 2043. The structure is 76 ft (23.2 m) long and 27 ft wide. If it were closed, the detour would be 2.5 mi (4 km).

CarriesLrd Highland DR
CrossesArtus Creek
Location1.1M E JCT Sth 107
RouteCity Street 0
Coordinates44.95869, -89.82266
Functional classRural Local

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck9 ExcellentNo problems noted.
Superstructure9 ExcellentNo problems noted.
Substructure9 ExcellentNo problems noted.
Channel and channel protection8 Very GoodNo problems noted.
Last inspectionOctober 2023
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourFoundations stable; scour within limits of footing or piles
Structural evaluation9: Superior to present desirable criteria
Deck geometry5: Somewhat better than minimum adequacy to tolerate being left in place as is
Waterway adequacy6: Equal to present minimum criteria
Approach roadway alignment6: Equal to present minimum criteria
Operating rating53.9 US tons
Inventory rating41.8 US tons

Structure

Structure typeSlab
MaterialConcrete
DeckNot applicable
Main spans2
Design loadHL 93
Structure length76 ft (23.2 m)
Longest span38 ft (11.6 m)
Deck width27 ft (8.1 m)
Roadway width24 ft (7.3 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic110 (2023)
Projected traffic150 by 2043
Trucks5%
Lanes on structure2
Traffic directionTwo-way traffic
CarriesHighway
CrossesWaterway
Detour if closed2.5 mi (4 km)
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerTown or Township Highway Agency
Maintained byTown or Township Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedNone recorded
Estimated improvement cost—
NavigationNo navigation control on waterway

Frequently asked questions

When was Lrd Highland DR over Artus Creek built?

It was built in 2023, making it 2 years old in 2025.

What condition is Lrd Highland DR over Artus Creek in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in October 2023.

How much traffic does Lrd Highland DR over Artus Creek carry?

About 110 vehicles per day (2023 count), of which roughly 5% are trucks.

How long is Lrd Highland DR over Artus Creek?

The structure is 76 ft (23.2 m) long with a longest span of 38 ft (11.6 m) and a deck 27 ft wide.

Who owns Lrd Highland DR over Artus Creek?

It is owned by the Town or Township Highway Agency.