No Data Entered over Dry Creek
PoorSkamania County, Washington · About 11 Miles SW of Trou · Structure no. 060308000000080
- Built
- 1962
- 63 years old
- Condition
- Poor
- inspected September 2023
- Type
- Stringer/Multi-beam or Girder
- Wood or Timber
- Length
- 32 ft
- 1 main span
- Daily traffic
- 118
- 1992 count
- Owner
- Federal
- U.S. Forest Service
About this bridge
No Data Entered over Dry Creek is a wood or timber stringer/multi-beam or girder carrying No Data Entered over Dry Creek in Skamania County, Washington. It was built in 1962, so it is 63 years old, older than the Washington average of 49.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in poor condition with a lowest component rating of 4 out of 9. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions.
It carries about 118 vehicles a day, roughly 10% of them trucks, projected to reach 177 by 2045. The structure is 32 ft (9.9 m) long and 16 ft wide. If it were closed, the detour would be 620.7 mi (999 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 4 Poor | Advanced section loss, deterioration, spalling or scour. |
| Superstructure | 6 Satisfactory | Structural elements show some minor deterioration. |
| Substructure | 6 Satisfactory | Structural elements show some minor deterioration. |
| Channel and channel protection | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was No Data Entered over Dry Creek built?
It was built in 1962, making it 63 years old in 2025.
What condition is No Data Entered over Dry Creek in?
The National Bridge Inventory rates it in poor condition. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions. The last reported inspection was in September 2023.
How much traffic does No Data Entered over Dry Creek carry?
About 118 vehicles per day (1992 count), of which roughly 10% are trucks.
How long is No Data Entered over Dry Creek?
The structure is 32 ft (9.9 m) long with a longest span of 31 ft (9.4 m) and a deck 16 ft wide.
Who owns No Data Entered over Dry Creek?
It is owned by the U.S. Forest Service.