March Point Road over Petroleum Pipelines
FairSkagit County, Washington · 1.6 N JCT SR 20 · Structure no. 084366000000000
- Built
- 1960
- 65 years old
- Condition
- Fair
- inspected September 2023
- Type
- Slab
- Concrete Continuous
- Length
- 44 ft
- 3 main spans
- Daily traffic
- 678
- 2023 count
- Owner
- County
- County Highway Agency
About this bridge
March Point Road over Petroleum Pipelines is a concrete continuous slab carrying March Point Road over Petroleum Pipelines in Skagit County, Washington. It was built in 1960, so it is 65 years old, older than the Washington average of 49.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 6 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
It carries about 678 vehicles a day, roughly 14% of them trucks, projected to reach 1,480 by 2041. The structure is 44 ft (13.5 m) long and 30 ft wide. If it were closed, the detour would be 3.7 mi (6 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 6 Satisfactory | Structural elements show some minor deterioration. |
| Superstructure | 6 Satisfactory | Structural elements show some minor deterioration. |
| Substructure | 6 Satisfactory | Structural elements show some minor deterioration. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was March Point Road over Petroleum Pipelines built?
It was built in 1960, making it 65 years old in 2025.
What condition is March Point Road over Petroleum Pipelines in?
The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in September 2023.
How much traffic does March Point Road over Petroleum Pipelines carry?
About 678 vehicles per day (2023 count), of which roughly 14% are trucks.
How long is March Point Road over Petroleum Pipelines?
The structure is 44 ft (13.5 m) long with a longest span of 14 ft (4.3 m) and a deck 30 ft wide.
Who owns March Point Road over Petroleum Pipelines?
It is owned by the County Highway Agency.