FairLewis County, Washington · 0.5 NW Packwood · Structure no. 082012000000000
- Built
- 1953
- 72 years old, rebuilt 1964
- Condition
- Fair
- inspected March 2023
- Type
- Truss - Thru
- Steel
- Length
- 392 ft
- 1 main span
- Daily traffic
- 1,331
- 2019 count
- Owner
- County
- County Highway Agency
About this bridge
Skate Creek Road over Cowlitz is a steel truss - thru carrying Skate Creek Road over Cowlitz in Lewis County, Washington. It was built in 1953 and reconstructed in 1964, so it is 72 years old, older than the Washington average of 49.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 5 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
It carries about 1,331 vehicles a day, roughly 12% of them trucks, projected to reach 2,404 by 2039. The structure is 392 ft (119.5 m) long and 31 ft wide. If it were closed, the detour would be 78.9 mi (127 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Superstructure | 6 Satisfactory | Structural elements show some minor deterioration. |
| Substructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Channel and channel protection | 8 Very Good | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Skate Creek Road over Cowlitz built?
It was built in 1953, making it 72 years old in 2025. It was reconstructed in 1964.
What condition is Skate Creek Road over Cowlitz in?
The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in March 2023.
How much traffic does Skate Creek Road over Cowlitz carry?
About 1,331 vehicles per day (2019 count), of which roughly 12% are trucks.
How long is Skate Creek Road over Cowlitz?
The structure is 392 ft (119.5 m) long with a longest span of 250 ft (76.2 m) and a deck 31 ft wide.
Who owns Skate Creek Road over Cowlitz?
It is owned by the County Highway Agency.