Redmond Ridge NE over Wetland
GoodKing County, Washington · 300 NW of NE 80th Street · Structure no. 087124000000000
- Built
- 2001
- 24 years old
- Condition
- Good
- inspected May 2023
- Type
- Stringer/Multi-beam or Girder
- Prestressed Concrete Continuous
- Length
- 195 ft
- 3 main spans
- Daily traffic
- 5,998
- 2022 count
- Owner
- County
- County Highway Agency
About this bridge
Redmond Ridge NE over Wetland is a prestressed concrete continuous stringer/multi-beam or girder carrying Redmond Ridge NE over Wetland in King County, Washington. It was built in 2001, so it is 24 years old, younger than the Washington average of 49.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 5,998 vehicles a day, roughly 1% of them trucks, projected to reach 10,834 by 2042. The structure is 195 ft (59.4 m) long and 49 ft wide. If it were closed, the detour would be 6.8 mi (11 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
| Channel and channel protection | 8 Very Good | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Redmond Ridge NE over Wetland built?
It was built in 2001, making it 24 years old in 2025.
What condition is Redmond Ridge NE over Wetland in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in May 2023.
How much traffic does Redmond Ridge NE over Wetland carry?
About 5,998 vehicles per day (2022 count), of which roughly 1% are trucks.
How long is Redmond Ridge NE over Wetland?
The structure is 195 ft (59.4 m) long with a longest span of 65 ft (19.8 m) and a deck 49 ft wide.
Who owns Redmond Ridge NE over Wetland?
It is owned by the County Highway Agency.