I-90 E-S Ramp over I-5/AIRPORT Way Ramp
GoodKing County, Washington · JCT I-5 · Structure no. 000000OC0000000
- Built
- 1965
- 60 years old, rebuilt 1991
- Condition
- Good
- inspected April 2023
- Type
- Box Beam or Girders - Single or Spread
- Prestressed Concrete Continuous
- Length
- 640 ft
- 2 main spans
- Daily traffic
- 9,815
- 2012 count
- Owner
- State
- State Highway Agency
About this bridge
I-90 E-S Ramp over I-5/AIRPORT Way Ramp is a prestressed concrete continuous box beam or girders - single or spread carrying I-90 E-S Ramp over I-5/AIRPORT Way Ramp in King County, Washington. It was built in 1965 and reconstructed in 1991, so it is 60 years old, older than the Washington average of 49.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 9,815 vehicles a day, roughly 5% of them trucks, projected to reach 16,411 by 2036. The structure is 640 ft (195.1 m) long and 28 ft wide. If it were closed, the detour would be 1.9 mi (3 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was I-90 E-S Ramp over I-5/AIRPORT Way Ramp built?
It was built in 1965, making it 60 years old in 2025. It was reconstructed in 1991.
What condition is I-90 E-S Ramp over I-5/AIRPORT Way Ramp in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in April 2023.
How much traffic does I-90 E-S Ramp over I-5/AIRPORT Way Ramp carry?
About 9,815 vehicles per day (2012 count), of which roughly 5% are trucks.
How long is I-90 E-S Ramp over I-5/AIRPORT Way Ramp?
The structure is 640 ft (195.1 m) long with a longest span of 156 ft (47.5 m) and a deck 28 ft wide.
Who owns I-90 E-S Ramp over I-5/AIRPORT Way Ramp?
It is owned by the State Highway Agency.