C3021 over East Putney Brook
PoorPosted for loadWindham County, Vermont · 0.2 MI to JCT W CL3 TH17 · Structure no. 101313002913131
- Built
- 1930
- 95 years old, rebuilt 1994
- Condition
- Poor
- inspected April 2024
- Type
- Stringer/Multi-beam or Girder
- Steel
- Length
- 37 ft
- 1 main span
- Daily traffic
- 20
- 2019 count
- Owner
- Town / Township
- Town or Township Highway Agency
About this bridge
C3021 over East Putney Brook is a steel stringer/multi-beam or girder carrying C3021 over East Putney Brook in Windham County, Vermont. It was built in 1930 and reconstructed in 1994, so it is 95 years old, older than the Vermont average of 60.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in poor condition with a lowest component rating of 4 out of 9. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions. Its operating status is: posted for load restriction.
It carries about 20 vehicles a day, roughly 2% of them trucks, projected to reach 21 by 2029. The structure is 37 ft (11.3 m) long and 16 ft wide. If it were closed, the detour would be 98.8 mi (159 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 8 Very Good | No problems noted. |
| Superstructure | 6 Satisfactory | Structural elements show some minor deterioration. |
| Substructure | 4 Poor | Advanced section loss, deterioration, spalling or scour. |
| Channel and channel protection | 4 Poor | Advanced section loss, deterioration, spalling or scour. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was C3021 over East Putney Brook built?
It was built in 1930, making it 95 years old in 2025. It was reconstructed in 1994.
What condition is C3021 over East Putney Brook in?
The National Bridge Inventory rates it in poor condition. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions. The last reported inspection was in April 2024.
How much traffic does C3021 over East Putney Brook carry?
About 20 vehicles per day (2019 count), of which roughly 2% are trucks.
How long is C3021 over East Putney Brook?
The structure is 37 ft (11.3 m) long with a longest span of 35 ft (10.7 m) and a deck 16 ft wide.
Who owns C3021 over East Putney Brook?
It is owned by the Town or Township Highway Agency.