SH 183 Wbfr over Future IH20WB to SH121NB
GoodTarrant County, Texas · 0.15 Mi. E. of SH 121 · Structure no. 022200050402482
- Built
- 2013
- 12 years old
- Condition
- Good
- inspected June 2024
- Type
- Stringer/Multi-beam or Girder
- Prestressed Concrete
- Length
- 84 ft
- 1 main span
- Daily traffic
- 8,570
- 2024 count
- Owner
- State
- State Highway Agency
About this bridge
SH 183 Wbfr over Future IH20WB to SH121NB is a prestressed concrete stringer/multi-beam or girder carrying SH 183 Wbfr over Future IH20WB to SH121NB in Tarrant County, Texas. It was built in 2013, so it is 12 years old, younger than the Texas average of 44.4 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 8,570 vehicles a day, roughly 5% of them trucks, projected to reach 4,400 by 2033. The structure is 84 ft (25.7 m) long and 43 ft wide. If it were closed, the detour would be 1.9 mi (3 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 8 Very Good | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was SH 183 Wbfr over Future IH20WB to SH121NB built?
It was built in 2013, making it 12 years old in 2025.
What condition is SH 183 Wbfr over Future IH20WB to SH121NB in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in June 2024.
How much traffic does SH 183 Wbfr over Future IH20WB to SH121NB carry?
About 8,570 vehicles per day (2024 count), of which roughly 5% are trucks.
How long is SH 183 Wbfr over Future IH20WB to SH121NB?
The structure is 84 ft (25.7 m) long with a longest span of 84 ft (25.7 m) and a deck 43 ft wide.
Who owns SH 183 Wbfr over Future IH20WB to SH121NB?
It is owned by the State Highway Agency.