US Bridges

FM 892 over Petronila Creek

FairPosted for load

Nueces County, Texas · 2.8 MI N of FM 70 · Structure no. 161780108804005

Built
1955
70 years old
Condition
Fair
inspected July 2024
Type
Stringer/Multi-beam or Girder
Steel Continuous
Length
275 ft
3 main spans
Daily traffic
490
2022 count
Owner
State
State Highway Agency

About this bridge

FM 892 over Petronila Creek is a steel continuous stringer/multi-beam or girder carrying FM 892 over Petronila Creek in Nueces County, Texas. It was built in 1955, so it is 70 years old, older than the Texas average of 44.4 years.

The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 6 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. Its operating status is: posted for load restriction.

It carries about 490 vehicles a day, roughly 4% of them trucks, projected to reach 340 by 2033. The structure is 275 ft (83.8 m) long and 26 ft wide. If it were closed, the detour would be 19.9 mi (32 km).

CarriesFM 892
CrossesPetronila Creek
Location2.8 MI N of FM 70
RouteState Highway 892
StateTexas
Coordinates27.61677, -97.66374
Functional classRural Major Collector

Condition and inspection

Fair

The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.

ComponentRatingMeaning
Deck6 SatisfactoryStructural elements show some minor deterioration.
Superstructure6 SatisfactoryStructural elements show some minor deterioration.
Substructure6 SatisfactoryStructural elements show some minor deterioration.
Channel and channel protection6 SatisfactoryStructural elements show some minor deterioration.
Last inspectionJuly 2024
Inspection intervalevery 24 months
Operating statusPosted for load restriction
ScourFoundations stable; scour within limits of footing or piles
Structural evaluation5: Somewhat better than minimum adequacy to tolerate being left in place as is
Deck geometry4: Meets minimum tolerable limits to be left in place as is
Waterway adequacy8: Equal to present desirable criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating36 US tons
Inventory rating22 US tons

Structure

MaterialSteel Continuous
DeckConcrete, cast-in-place
Main spans3 (+2 approach)
Design loadOther
Structure length275 ft (83.8 m)
Longest span75 ft (22.9 m)
Deck width26 ft (7.8 m)
Roadway width23 ft (7 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic490 (2022)
Projected traffic340 by 2033
Trucks4%
Lanes on structure2
Traffic directionTwo-way traffic
CarriesHighway
CrossesWaterway
Detour if closed19.9 mi (32 km)
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerState Highway Agency
Maintained byState Highway Agency
Historic statusPossibly eligible for the National Register; requires further investigation
Work proposedNone recorded
Estimated improvement cost—
NavigationNo navigation control on waterway

Frequently asked questions

When was FM 892 over Petronila Creek built?

It was built in 1955, making it 70 years old in 2025.

What condition is FM 892 over Petronila Creek in?

The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in July 2024.

How much traffic does FM 892 over Petronila Creek carry?

About 490 vehicles per day (2022 count), of which roughly 4% are trucks.

How long is FM 892 over Petronila Creek?

The structure is 275 ft (83.8 m) long with a longest span of 75 ft (22.9 m) and a deck 26 ft wide.

Who owns FM 892 over Petronila Creek?

It is owned by the State Highway Agency.