US Bridges

W-19 Off Ramp over Quaker Avenue

Good

Lubbock County, Texas · 0.35 MI SW of SH 114 · Structure no. 051520038001048

Built
2009
16 years old
Condition
Good
inspected November 2023
Type
Stringer/Multi-beam or Girder
Prestressed Concrete
Length
323 ft
3 main spans
Daily traffic
3,900
2015 count
Owner
State
State Highway Agency

About this bridge

W-19 Off Ramp over Quaker Avenue is a prestressed concrete stringer/multi-beam or girder carrying W-19 Off Ramp over Quaker Avenue in Lubbock County, Texas. It was built in 2009, so it is 16 years old, younger than the Texas average of 44.4 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 3,900 vehicles a day, roughly 5% of them trucks, projected to reach 6,800 by 2035. The structure is 323 ft (98.5 m) long and 28 ft wide.

CarriesW-19 Off Ramp
CrossesQuaker Avenue
Location0.35 MI SW of SH 114
RouteU.S. Route 82
StateTexas
Coordinates33.57472, -101.90517
Functional classUrban Principal Arterial - Other Freeway or Expressway

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck7 GoodSome minor problems.
Superstructure7 GoodSome minor problems.
Substructure7 GoodSome minor problems.
Last inspectionNovember 2023
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourBridge not over waterway
Structural evaluation7: Better than present minimum criteria
Deck geometry7: Better than present minimum criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating60 US tons
Inventory rating36 US tons

Structure

MaterialPrestressed Concrete
DeckConcrete, cast-in-place
Main spans3
Design loadHS 20
Structure length323 ft (98.5 m)
Longest span119 ft (36.3 m)
Deck width28 ft (8.5 m)
Roadway width25 ft (7.7 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic3,900 (2015)
Projected traffic6,800 by 2035
Trucks5%
Lanes on structure1
Traffic directionOne-way traffic
CarriesHighway
CrossesHighway
Detour if closed—
TollOn a free road
National Highway SystemNo
Strategic Highway NetworkInterstate STRAHNET route

Ownership and planned work

OwnerState Highway Agency
Maintained byState Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedNone recorded
Estimated improvement cost—
NavigationNot applicable (no waterway)

Frequently asked questions

When was W-19 Off Ramp over Quaker Avenue built?

It was built in 2009, making it 16 years old in 2025.

What condition is W-19 Off Ramp over Quaker Avenue in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in November 2023.

How much traffic does W-19 Off Ramp over Quaker Avenue carry?

About 3,900 vehicles per day (2015 count), of which roughly 5% are trucks.

How long is W-19 Off Ramp over Quaker Avenue?

The structure is 323 ft (98.5 m) long with a longest span of 119 ft (36.3 m) and a deck 28 ft wide.

Who owns W-19 Off Ramp over Quaker Avenue?

It is owned by the State Highway Agency.