Aldine Mail Rt over Hardy Toll RD & UP RR
GoodHarris County, Texas · 2.15 MI S of Aldine Bend · Structure no. 121020AA5208001
- Built
- 1987
- 38 years old, rebuilt 2013
- Condition
- Good
- inspected December 2023
- Type
- Stringer/Multi-beam or Girder
- Prestressed Concrete
- Length
- 550 ft
- 5 main spans
- Daily traffic
- 11,470
- 2010 count
- Owner
- County
- County Highway Agency
About this bridge
Aldine Mail Rt over Hardy Toll RD & UP RR is a prestressed concrete stringer/multi-beam or girder carrying Aldine Mail Rt over Hardy Toll RD & UP RR in Harris County, Texas. It was built in 1987 and reconstructed in 2013, so it is 38 years old, younger than the Texas average of 44.4 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 11,470 vehicles a day, roughly 10% of them trucks, projected to reach 15,000 by 2030. The structure is 550 ft (167.6 m) long and 94 ft wide. If it were closed, the detour would be 1.9 mi (3 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Aldine Mail Rt over Hardy Toll RD & UP RR built?
It was built in 1987, making it 38 years old in 2025. It was reconstructed in 2013.
What condition is Aldine Mail Rt over Hardy Toll RD & UP RR in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in December 2023.
How much traffic does Aldine Mail Rt over Hardy Toll RD & UP RR carry?
About 11,470 vehicles per day (2010 count), of which roughly 10% are trucks.
How long is Aldine Mail Rt over Hardy Toll RD & UP RR?
The structure is 550 ft (167.6 m) long with a longest span of 90 ft (27.4 m) and a deck 94 ft wide.
Who owns Aldine Mail Rt over Hardy Toll RD & UP RR?
It is owned by the County Highway Agency.