US 90A over West Sandy Creek
GoodColorado County, Texas · 0.1 MI E of Lavaca C/L · Structure no. 130450044602042
- Built
- 2022
- 3 years old
- Condition
- Good
- inspected March 2023
- Type
- Stringer/Multi-beam or Girder
- Prestressed Concrete
- Length
- 356 ft
- 5 main spans
- Daily traffic
- 2,866
- 2021 count
- Owner
- State
- State Highway Agency
About this bridge
US 90A over West Sandy Creek is a prestressed concrete stringer/multi-beam or girder carrying US 90A over West Sandy Creek in Colorado County, Texas. It was built in 2022, so it is 3 years old, younger than the Texas average of 44.4 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 2,866 vehicles a day, roughly 15% of them trucks, projected to reach 3,668 by 2041. The structure is 356 ft (108.5 m) long and 46 ft wide. If it were closed, the detour would be 14.9 mi (24 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
| Channel and channel protection | 6 Satisfactory | Structural elements show some minor deterioration. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was US 90A over West Sandy Creek built?
It was built in 2022, making it 3 years old in 2025.
What condition is US 90A over West Sandy Creek in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in March 2023.
How much traffic does US 90A over West Sandy Creek carry?
About 2,866 vehicles per day (2021 count), of which roughly 15% are trucks.
How long is US 90A over West Sandy Creek?
The structure is 356 ft (108.5 m) long with a longest span of 93 ft (28.3 m) and a deck 46 ft wide.
Who owns US 90A over West Sandy Creek?
It is owned by the State Highway Agency.