East 30th Street over Ccwid #1 North Drain
GoodPosted for loadCameron County, Texas · 0.20 MI NE of FM 1419 · Structure no. 210310C01917001
- Built
- 1940
- 85 years old
- Condition
- Good
- inspected March 2024
- Type
- Slab
- Concrete
- Length
- 52 ft
- 2 main spans
- Daily traffic
- 4,113
- 2019 count
- Owner
- City
- City or Municipal Highway Agency
About this bridge
East 30th Street over Ccwid #1 North Drain is a concrete slab carrying East 30th Street over Ccwid #1 North Drain in Cameron County, Texas. It was built in 1940, so it is 85 years old, older than the Texas average of 44.4 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. Its operating status is: posted for load restriction.
It carries about 4,113 vehicles a day, roughly 3% of them trucks, projected to reach 5,758 by 2042. The structure is 52 ft (15.9 m) long and 31 ft wide. If it were closed, the detour would be 1.9 mi (3 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
| Channel and channel protection | 6 Satisfactory | Structural elements show some minor deterioration. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was East 30th Street over Ccwid #1 North Drain built?
It was built in 1940, making it 85 years old in 2025.
What condition is East 30th Street over Ccwid #1 North Drain in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in March 2024.
How much traffic does East 30th Street over Ccwid #1 North Drain carry?
About 4,113 vehicles per day (2019 count), of which roughly 3% are trucks.
How long is East 30th Street over Ccwid #1 North Drain?
The structure is 52 ft (15.9 m) long with a longest span of 25 ft (7.6 m) and a deck 31 ft wide.
Who owns East 30th Street over Ccwid #1 North Drain?
It is owned by the City or Municipal Highway Agency.