Mc Hard RD EB over Drainage Ditch
GoodBrazoria County, Texas · 1.35 MI E of SH 288 · Structure no. 120200AA2004003
- Built
- 2010
- 15 years old
- Condition
- Good
- inspected November 2023
- Type
- Other
- Prestressed Concrete
- Length
- 130 ft
- 3 main spans
- Daily traffic
- 1,750
- 2011 count
- Owner
- County
- County Highway Agency
About this bridge
Mc Hard RD EB over Drainage Ditch is a prestressed concrete other carrying Mc Hard RD EB over Drainage Ditch in Brazoria County, Texas. It was built in 2010, so it is 15 years old, younger than the Texas average of 44.4 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 1,750 vehicles a day, roughly 1% of them trucks, projected to reach 3,500 by 2031. The structure is 130 ft (39.6 m) long and 34 ft wide. If it were closed, the detour would be 1.2 mi (2 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 8 Very Good | No problems noted. |
| Substructure | 7 Good | Some minor problems. |
| Channel and channel protection | 8 Very Good | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Mc Hard RD EB over Drainage Ditch built?
It was built in 2010, making it 15 years old in 2025.
What condition is Mc Hard RD EB over Drainage Ditch in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in November 2023.
How much traffic does Mc Hard RD EB over Drainage Ditch carry?
About 1,750 vehicles per day (2011 count), of which roughly 1% are trucks.
How long is Mc Hard RD EB over Drainage Ditch?
The structure is 130 ft (39.6 m) long with a longest span of 50 ft (15.2 m) and a deck 34 ft wide.
Who owns Mc Hard RD EB over Drainage Ditch?
It is owned by the County Highway Agency.