FM 114 over Tanyard Creek

Good

Bowie County, Texas · 1.00 MI W of US 259 · Structure no. 190190157002001

Built
1956
69 years old
Condition
Good
inspected June 2024
Type
Culvert
Concrete
Length
35 ft
4 main spans
Daily traffic
251
2020 count
Owner
State
State Highway Agency

About this bridge

FM 114 over Tanyard Creek is a concrete culvert carrying FM 114 over Tanyard Creek in Bowie County, Texas. It was built in 1956, so it is 69 years old, older than the Texas average of 44.4 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 251 vehicles a day, roughly 13% of them trucks, projected to reach 280 by 2033. The structure is 35 ft (10.7 m) long. If it were closed, the detour would be 14.9 mi (24 km).

CarriesFM 114
CrossesTanyard Creek
Location1.00 MI W of US 259
RouteState Highway 114
StateTexas
Coordinates33.60294, -94.67644
Functional classRural Major Collector

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Channel and channel protection7 GoodSome minor problems.
Culvert7 GoodSome minor problems.
Last inspectionJune 2024
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourCountermeasures installed to correct a previously existing problem
Structural evaluation6: Equal to present minimum criteria
Waterway adequacy6: Equal to present minimum criteria
Approach roadway alignment6: Equal to present minimum criteria
Operating rating44 US tons
Inventory rating26 US tons

Structure

Structure typeCulvert
MaterialConcrete
DeckNot applicable
Main spans4
Design loadOther
Structure length35 ft (10.7 m)
Longest span8 ft (2.4 m)
Deck width0 ft (0 m)
Roadway width0 ft (0 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic251 (2020)
Projected traffic280 by 2033
Trucks13%
Lanes on structure2
Traffic directionTwo-way traffic
CarriesHighway
CrossesWaterway
Detour if closed14.9 mi (24 km)
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerState Highway Agency
Maintained byState Highway Agency
Historic statusPossibly eligible for the National Register; requires further investigation
Work proposedNone recorded
Estimated improvement cost—
NavigationNo navigation control on waterway

Frequently asked questions

When was FM 114 over Tanyard Creek built?

It was built in 1956, making it 69 years old in 2025.

What condition is FM 114 over Tanyard Creek in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in June 2024.

How much traffic does FM 114 over Tanyard Creek carry?

About 251 vehicles per day (2020 count), of which roughly 13% are trucks.

How long is FM 114 over Tanyard Creek?

The structure is 35 ft (10.7 m) long with a longest span of 8 ft (2.4 m).

Who owns FM 114 over Tanyard Creek?

It is owned by the State Highway Agency.