Spur Crossover Roa over West Prong Lpr
FairSevier County, Tennessee · 3.0 Miles North from NPS · Structure no. 5460084P0000000
- Built
- 1960
- 65 years old
- Condition
- Fair
- inspected June 2024
- Type
- Stringer/Multi-beam or Girder
- Prestressed Concrete
- Length
- 188 ft
- 3 main spans
- Daily traffic
- 4,332
- 2019 count
- Owner
- Federal
- National Park Service
About this bridge
Spur Crossover Roa over West Prong Lpr is a prestressed concrete stringer/multi-beam or girder carrying Spur Crossover Roa over West Prong Lpr in Sevier County, Tennessee. It was built in 1960, so it is 65 years old, older than the Tennessee average of 47.4 years.
The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 5 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
It carries about 4,332 vehicles a day, roughly 1% of them trucks, projected to reach 4,777 by 2039. The structure is 188 ft (57.2 m) long and 33 ft wide. If it were closed, the detour would be 9.9 mi (16 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Substructure | 6 Satisfactory | Structural elements show some minor deterioration. |
| Channel and channel protection | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Spur Crossover Roa over West Prong Lpr built?
It was built in 1960, making it 65 years old in 2025.
What condition is Spur Crossover Roa over West Prong Lpr in?
The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in June 2024.
How much traffic does Spur Crossover Roa over West Prong Lpr carry?
About 4,332 vehicles per day (2019 count), of which roughly 1% are trucks.
How long is Spur Crossover Roa over West Prong Lpr?
The structure is 188 ft (57.2 m) long with a longest span of 63 ft (19.2 m) and a deck 33 ft wide.
Who owns Spur Crossover Roa over West Prong Lpr?
It is owned by the National Park Service.