Nfa A224 841853G over Southern Railway
FairMorgan County, Tennessee · At Sunbright E of US27 · Structure no. 650A2240001
- Built
- 1975
- 50 years old
- Condition
- Fair
- inspected January 2025
- Type
- Box Beam or Girders - Multiple
- Prestressed Concrete
- Length
- 102 ft
- 1 main span
- Daily traffic
- 430
- 2020 count
- Owner
- City
- City or Municipal Highway Agency
About this bridge
Nfa A224 841853G over Southern Railway is a prestressed concrete box beam or girders - multiple carrying Nfa A224 841853G over Southern Railway in Morgan County, Tennessee. It was built in 1975, so it is 50 years old, older than the Tennessee average of 47.4 years.
The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 5 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
It carries about 430 vehicles a day, roughly 2% of them trucks, projected to reach 688 by 2041. The structure is 102 ft (31.1 m) long and 21 ft wide. If it were closed, the detour would be 3.7 mi (6 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 6 Satisfactory | Structural elements show some minor deterioration. |
| Superstructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Substructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Nfa A224 841853G over Southern Railway built?
It was built in 1975, making it 50 years old in 2025.
What condition is Nfa A224 841853G over Southern Railway in?
The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in January 2025.
How much traffic does Nfa A224 841853G over Southern Railway carry?
About 430 vehicles per day (2020 count), of which roughly 2% are trucks.
How long is Nfa A224 841853G over Southern Railway?
The structure is 102 ft (31.1 m) long with a longest span of 99 ft (30.2 m) and a deck 21 ft wide.
Who owns Nfa A224 841853G over Southern Railway?
It is owned by the City or Municipal Highway Agency.