US212 P over Redwater Rv
FairButte County, South Dakota · 1E JCT US85-BELLE Fourche · Structure no. 000000010105376
- Built
- 1995
- 30 years old
- Condition
- Fair
- inspected April 2024
- Type
- Slab
- Concrete Continuous
- Length
- 353 ft
- 8 main spans
- Daily traffic
- 1,418
- 2022 count
- Owner
- Town / Township
- Town or Township Highway Agency
About this bridge
US212 P over Redwater Rv is a concrete continuous slab carrying US212 P over Redwater Rv in Butte County, South Dakota. It was built in 1995, so it is 30 years old, younger than the South Dakota average of 48.9 years.
The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 6 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
It carries about 1,418 vehicles a day, roughly 7% of them trucks, projected to reach 1,837 by 2032. The structure is 353 ft (107.7 m) long and 39 ft wide. If it were closed, the detour would be 1.2 mi (2 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 6 Satisfactory | Structural elements show some minor deterioration. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
| Channel and channel protection | 8 Very Good | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was US212 P over Redwater Rv built?
It was built in 1995, making it 30 years old in 2025.
What condition is US212 P over Redwater Rv in?
The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in April 2024.
How much traffic does US212 P over Redwater Rv carry?
About 1,418 vehicles per day (2022 count), of which roughly 7% are trucks.
How long is US212 P over Redwater Rv?
The structure is 353 ft (107.7 m) long with a longest span of 44 ft (13.3 m) and a deck 39 ft wide.
Who owns US212 P over Redwater Rv?
It is owned by the Town or Township Highway Agency.