Sc 56 over I-85 (new)
GoodSpartanburg County, South Carolina · 3.5 MI NW of Spartanburg · Structure no. 000000000008591
- Built
- 1992
- 33 years old
- Condition
- Good
- inspected February 2024
- Type
- Stringer/Multi-beam or Girder
- Steel Continuous
- Length
- 274 ft
- 4 main spans
- Daily traffic
- 11,000
- 2023 count
- Owner
- State
- State Highway Agency
About this bridge
Sc 56 over I-85 (new) is a steel continuous stringer/multi-beam or girder carrying Sc 56 over I-85 (new) in Spartanburg County, South Carolina. It was built in 1992, so it is 33 years old, younger than the South Carolina average of 48 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 11,000 vehicles a day, roughly 6% of them trucks, projected to reach 15,950 by 2043. The structure is 274 ft (83.5 m) long and 78 ft wide. If it were closed, the detour would be 1.2 mi (2 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 8 Very Good | No problems noted. |
| Substructure | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Sc 56 over I-85 (new) built?
It was built in 1992, making it 33 years old in 2025.
What condition is Sc 56 over I-85 (new) in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in February 2024.
How much traffic does Sc 56 over I-85 (new) carry?
About 11,000 vehicles per day (2023 count), of which roughly 6% are trucks.
How long is Sc 56 over I-85 (new)?
The structure is 274 ft (83.5 m) long with a longest span of 96 ft (29.3 m) and a deck 78 ft wide.
Who owns Sc 56 over I-85 (new)?
It is owned by the State Highway Agency.