S-19-275 over Wimbley Branch
GoodEdgefield County, South Carolina · 6.3MI SE Johnston · Structure no. 000000000004112
- Built
- 2016
- 9 years old
- Condition
- Good
- inspected February 2025
- Type
- Slab
- Prestressed Concrete
- Length
- 90 ft
- 2 main spans
- Daily traffic
- 150
- 2023 count
- Owner
- State
- State Highway Agency
About this bridge
S-19-275 over Wimbley Branch is a prestressed concrete slab carrying S-19-275 over Wimbley Branch in Edgefield County, South Carolina. It was built in 2016, so it is 9 years old, younger than the South Carolina average of 48 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 8 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 150 vehicles a day, roughly 5% of them trucks, projected to reach 192 by 2043. The structure is 90 ft (27.4 m) long and 36 ft wide. If it were closed, the detour would be 3.1 mi (5 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 8 Very Good | No problems noted. |
| Superstructure | 8 Very Good | No problems noted. |
| Substructure | 8 Very Good | No problems noted. |
| Channel and channel protection | 6 Satisfactory | Structural elements show some minor deterioration. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was S-19-275 over Wimbley Branch built?
It was built in 2016, making it 9 years old in 2025.
What condition is S-19-275 over Wimbley Branch in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in February 2025.
How much traffic does S-19-275 over Wimbley Branch carry?
About 150 vehicles per day (2023 count), of which roughly 5% are trucks.
How long is S-19-275 over Wimbley Branch?
The structure is 90 ft (27.4 m) long with a longest span of 70 ft (21.3 m) and a deck 36 ft wide.
Who owns S-19-275 over Wimbley Branch?
It is owned by the State Highway Agency.