I-95 Ramp Cb over Wellington Av & AMTRAK
PoorProvidence County, Rhode Island · 0.1 MI E of JCT Ri 10 · Structure no. 000000000006620
- Built
- 1965
- 60 years old, rebuilt 1997
- Condition
- Poor
- inspected August 2023
- Type
- Stringer/Multi-beam or Girder
- Steel
- Length
- 291 ft
- 3 main spans
- Daily traffic
- 7,776
- 2023 count
- Owner
- State
- State Highway Agency
About this bridge
I-95 Ramp Cb over Wellington Av & AMTRAK is a steel stringer/multi-beam or girder carrying I-95 Ramp Cb over Wellington Av & AMTRAK in Providence County, Rhode Island. It was built in 1965 and reconstructed in 1997, so it is 60 years old, older than the Rhode Island average of 54.5 years.
The most recent inspection reported to the Federal Highway Administration rates it in poor condition with a lowest component rating of 4 out of 9. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions.
It carries about 7,776 vehicles a day, roughly 4% of them trucks, projected to reach 324 by 2041. The structure is 291 ft (88.7 m) long and 29 ft wide. If it were closed, the detour would be 0.6 mi (1 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Superstructure | 4 Poor | Advanced section loss, deterioration, spalling or scour. |
| Substructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was I-95 Ramp Cb over Wellington Av & AMTRAK built?
It was built in 1965, making it 60 years old in 2025. It was reconstructed in 1997.
What condition is I-95 Ramp Cb over Wellington Av & AMTRAK in?
The National Bridge Inventory rates it in poor condition. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions. The last reported inspection was in August 2023.
How much traffic does I-95 Ramp Cb over Wellington Av & AMTRAK carry?
About 7,776 vehicles per day (2023 count), of which roughly 4% are trucks.
How long is I-95 Ramp Cb over Wellington Av & AMTRAK?
The structure is 291 ft (88.7 m) long with a longest span of 157 ft (47.9 m) and a deck 29 ft wide.
Who owns I-95 Ramp Cb over Wellington Av & AMTRAK?
It is owned by the State Highway Agency.