Pr 185 20.5 KM over Gurabo River KM 20.41
FairPosted for loadJuncos Municipio, Puerto Rico · 2 KM N N W of Juncos · Structure no. 007351
- Built
- 1955
- 70 years old
- Condition
- Fair
- inspected April 2024
- Type
- Tee Beam
- Concrete Continuous
- Length
- 197 ft
- 5 main spans
- Daily traffic
- 14,700
- 2017 count
- Owner
- State
- State Highway Agency
About this bridge
Pr 185 20.5 KM over Gurabo River KM 20.41 is a concrete continuous tee beam carrying Pr 185 20.5 KM over Gurabo River KM 20.41 in Juncos Municipio, Puerto Rico. It was built in 1955, so it is 70 years old, older than the Puerto Rico average of 51.2 years.
The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 5 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. Its operating status is: posted for load restriction.
It carries about 14,700 vehicles a day, roughly 4% of them trucks, projected to reach 18,700 by 2025. The structure is 197 ft (59.9 m) long and 29 ft wide. If it were closed, the detour would be 5.6 mi (9 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Superstructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Substructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Channel and channel protection | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Pr 185 20.5 KM over Gurabo River KM 20.41 built?
It was built in 1955, making it 70 years old in 2025.
What condition is Pr 185 20.5 KM over Gurabo River KM 20.41 in?
The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in April 2024.
How much traffic does Pr 185 20.5 KM over Gurabo River KM 20.41 carry?
About 14,700 vehicles per day (2017 count), of which roughly 4% are trucks.
How long is Pr 185 20.5 KM over Gurabo River KM 20.41?
The structure is 197 ft (59.9 m) long with a longest span of 51 ft (15.5 m) and a deck 29 ft wide.
Who owns Pr 185 20.5 KM over Gurabo River KM 20.41?