Off Sol ST 0.3 KM over Santa Catalina Creek
FairJayuya Municipio, Puerto Rico · 2 KM West of Jayuya · Structure no. 019801
- Built
- 1990
- 35 years old
- Condition
- Fair
- inspected November 2023
- Type
- Stringer/Multi-beam or Girder
- Steel
- Length
- 23 ft
- 1 main span
- Daily traffic
- 7,500
- 2017 count
- Owner
- City
- City or Municipal Highway Agency
About this bridge
Off Sol ST 0.3 KM over Santa Catalina Creek is a steel stringer/multi-beam or girder carrying Off Sol ST 0.3 KM over Santa Catalina Creek in Jayuya Municipio, Puerto Rico. It was built in 1990, so it is 35 years old, younger than the Puerto Rico average of 51.2 years.
The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 6 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
It carries about 7,500 vehicles a day, roughly 1% of them trucks, projected to reach 10,100 by 2025. The structure is 23 ft (6.9 m) long and 14 ft wide. If it were closed, the detour would be 1.2 mi (2 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 6 Satisfactory | Structural elements show some minor deterioration. |
| Superstructure | 6 Satisfactory | Structural elements show some minor deterioration. |
| Substructure | 6 Satisfactory | Structural elements show some minor deterioration. |
| Channel and channel protection | 6 Satisfactory | Structural elements show some minor deterioration. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Off Sol ST 0.3 KM over Santa Catalina Creek built?
It was built in 1990, making it 35 years old in 2025.
What condition is Off Sol ST 0.3 KM over Santa Catalina Creek in?
The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in November 2023.
How much traffic does Off Sol ST 0.3 KM over Santa Catalina Creek carry?
About 7,500 vehicles per day (2017 count), of which roughly 1% are trucks.
How long is Off Sol ST 0.3 KM over Santa Catalina Creek?
The structure is 23 ft (6.9 m) long with a longest span of 21 ft (6.3 m) and a deck 14 ft wide.
Who owns Off Sol ST 0.3 KM over Santa Catalina Creek?
It is owned by the City or Municipal Highway Agency.