US Bridges

North Adams Street over Sprogels Run

PoorPosted for load

Montgomery County, Pennsylvania · S of Buchert RD 3027-A9 · Structure no. 000000000057161

Built
1960
65 years old
Condition
Poor
inspected October 2023
Type
Box Beam or Girders - Multiple
Prestressed Concrete
Length
30 ft
1 main span
Daily traffic
3,000
2019 count
Owner
Town / Township
Town or Township Highway Agency

About this bridge

North Adams Street over Sprogels Run is a prestressed concrete box beam or girders - multiple carrying North Adams Street over Sprogels Run in Montgomery County, Pennsylvania. It was built in 1960, so it is 65 years old, older than the Pennsylvania average of 54.8 years.

The most recent inspection reported to the Federal Highway Administration rates it in poor condition with a lowest component rating of 3 out of 9. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions. Its operating status is: posted for load restriction.

It carries about 3,000 vehicles a day, roughly 1% of them trucks, projected to reach 3,500 by 2039. The structure is 30 ft (9.1 m) long and 41 ft wide. If it were closed, the detour would be 1.2 mi (2 km).

CarriesNorth Adams Street
CrossesSprogels Run
LocationS of Buchert RD 3027-A9
RouteCity Street 0
Coordinates40.26069, -75.61961
Functional classRural Local

Condition and inspection

Poor

The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions.

ComponentRatingMeaning
Deck3 SeriousLoss of section, deterioration, spalling or scour have seriously affected primary structural components.
Superstructure3 SeriousLoss of section, deterioration, spalling or scour have seriously affected primary structural components.
Substructure5 FairAll primary structural elements are sound but may have minor section loss, cracking, spalling or scour.
Channel and channel protection5 FairAll primary structural elements are sound but may have minor section loss, cracking, spalling or scour.
Last inspectionOctober 2023
Inspection intervalevery 24 months
Operating statusPosted for load restriction
ScourFoundations stable; action required to protect exposed foundations
Structural evaluation3: Basically intolerable, requiring high priority of corrective action
Deck geometry2: Basically intolerable, requiring high priority of replacement
Waterway adequacy7: Better than present minimum criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating11 US tons
Inventory rating0 US tons

Structure

MaterialPrestressed Concrete
DeckOther
Main spans1
Design loadHS 20
Structure length30 ft (9.1 m)
Longest span28 ft (8.5 m)
Deck width41 ft (12.4 m)
Roadway width24 ft (7.3 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic3,000 (2019)
Projected traffic3,500 by 2039
Trucks1%
Lanes on structure2
Traffic directionTwo-way traffic
CarriesHighway
CrossesWaterway
Detour if closed1.2 mi (2 km)
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerTown or Township Highway Agency
Maintained byTown or Township Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedOther structural work, including hydraulic replacements
Estimated improvement cost—
NavigationNo navigation control on waterway

Frequently asked questions

When was North Adams Street over Sprogels Run built?

It was built in 1960, making it 65 years old in 2025.

What condition is North Adams Street over Sprogels Run in?

The National Bridge Inventory rates it in poor condition. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions. The last reported inspection was in October 2023.

How much traffic does North Adams Street over Sprogels Run carry?

About 3,000 vehicles per day (2019 count), of which roughly 1% are trucks.

How long is North Adams Street over Sprogels Run?

The structure is 30 ft (9.1 m) long with a longest span of 28 ft (8.5 m) and a deck 41 ft wide.

Who owns North Adams Street over Sprogels Run?

It is owned by the Town or Township Highway Agency.