SR 1059 Fedor RD over Harvey Creek
GoodLuzerne County, Pennsylvania · Lehman Twp 200 S TR 118 · Structure no. 000000000024043
- Built
- 1997
- 28 years old
- Condition
- Good
- inspected October 2022
- Type
- Box Beam or Girders - Multiple
- Prestressed Concrete
- Length
- 40 ft
- 1 main span
- Daily traffic
- 483
- 2024 count
- Owner
- State
- State Highway Agency
About this bridge
SR 1059 Fedor RD over Harvey Creek is a prestressed concrete box beam or girders - multiple carrying SR 1059 Fedor RD over Harvey Creek in Luzerne County, Pennsylvania. It was built in 1997, so it is 28 years old, younger than the Pennsylvania average of 54.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 483 vehicles a day, roughly 6% of them trucks, projected to reach 399 by 2032. The structure is 40 ft (12.2 m) long and 32 ft wide. If it were closed, the detour would be 8.1 mi (13 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 8 Very Good | No problems noted. |
| Substructure | 7 Good | Some minor problems. |
| Channel and channel protection | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was SR 1059 Fedor RD over Harvey Creek built?
It was built in 1997, making it 28 years old in 2025.
What condition is SR 1059 Fedor RD over Harvey Creek in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in October 2022.
How much traffic does SR 1059 Fedor RD over Harvey Creek carry?
About 483 vehicles per day (2024 count), of which roughly 6% are trucks.
How long is SR 1059 Fedor RD over Harvey Creek?
The structure is 40 ft (12.2 m) long with a longest span of 39 ft (11.9 m) and a deck 32 ft wide.
Who owns SR 1059 Fedor RD over Harvey Creek?
It is owned by the State Highway Agency.