Tyburn Rd/Brist P over Amtrak-Ny to Wash
GoodBucks County, Pennsylvania · 1.5MI.S.MORRISVIL. 39B09 · Structure no. 000000000007186
- Built
- 1955
- 70 years old, rebuilt 2015
- Condition
- Good
- inspected October 2023
- Type
- Stringer/Multi-beam or Girder
- Steel Continuous
- Length
- 291 ft
- 4 main spans
- Daily traffic
- 13,610
- 2024 count
- Owner
- State
- State Highway Agency
About this bridge
Tyburn Rd/Brist P over Amtrak-Ny to Wash is a steel continuous stringer/multi-beam or girder carrying Tyburn Rd/Brist P over Amtrak-Ny to Wash in Bucks County, Pennsylvania. It was built in 1955 and reconstructed in 2015, so it is 70 years old, older than the Pennsylvania average of 54.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 13,610 vehicles a day, roughly 21% of them trucks, projected to reach 21,706 by 2032. The structure is 291 ft (88.7 m) long and 70 ft wide. If it were closed, the detour would be 3.7 mi (6 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 8 Very Good | No problems noted. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Tyburn Rd/Brist P over Amtrak-Ny to Wash built?
It was built in 1955, making it 70 years old in 2025. It was reconstructed in 2015.
What condition is Tyburn Rd/Brist P over Amtrak-Ny to Wash in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in October 2023.
How much traffic does Tyburn Rd/Brist P over Amtrak-Ny to Wash carry?
About 13,610 vehicles per day (2024 count), of which roughly 21% are trucks.
How long is Tyburn Rd/Brist P over Amtrak-Ny to Wash?
The structure is 291 ft (88.7 m) long with a longest span of 104 ft (31.7 m) and a deck 70 ft wide.
Who owns Tyburn Rd/Brist P over Amtrak-Ny to Wash?
It is owned by the State Highway Agency.