HWY 002 over NE 223rd (fairview Ave)
FairMultnomah County, Oregon · 2.5 MI W Sandy River · Structure no. 17213 002 01522
- Built
- 1996
- 29 years old
- Condition
- Fair
- inspected April 2023
- Type
- Box Beam or Girders - Multiple
- Prestressed Concrete
- Length
- 127 ft
- 1 main span
- Daily traffic
- 56,101
- 2022 count
- Owner
- State
- State Highway Agency
About this bridge
HWY 002 over NE 223rd (fairview Ave) is a prestressed concrete box beam or girders - multiple carrying HWY 002 over NE 223rd (fairview Ave) in Multnomah County, Oregon. It was built in 1996, so it is 29 years old, younger than the Oregon average of 49.9 years.
The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 5 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
It carries about 56,101 vehicles a day, roughly 18% of them trucks, projected to reach 78,400 by 2042. The structure is 127 ft (38.6 m) long and 140 ft wide. If it were closed, the detour would be 1.9 mi (3 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 6 Satisfactory | Structural elements show some minor deterioration. |
| Superstructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Substructure | 6 Satisfactory | Structural elements show some minor deterioration. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was HWY 002 over NE 223rd (fairview Ave) built?
It was built in 1996, making it 29 years old in 2025.
What condition is HWY 002 over NE 223rd (fairview Ave) in?
The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in April 2023.
How much traffic does HWY 002 over NE 223rd (fairview Ave) carry?
About 56,101 vehicles per day (2022 count), of which roughly 18% are trucks.
How long is HWY 002 over NE 223rd (fairview Ave)?
The structure is 127 ft (38.6 m) long with a longest span of 127 ft (38.6 m) and a deck 140 ft wide.
Who owns HWY 002 over NE 223rd (fairview Ave)?
It is owned by the State Highway Agency.