US Bridges

Stage Coach RD over Lake Creek

Fair

Lane County, Oregon · 002 E Swisshome · Structure no. 39C515502001163

Built
1960
65 years old
Condition
Fair
inspected August 2023
Type
Box Beam or Girders - Multiple
Concrete Continuous
Length
264 ft
3 main spans
Daily traffic
382
2020 count
Owner
County
County Highway Agency

About this bridge

Stage Coach RD over Lake Creek is a concrete continuous box beam or girders - multiple carrying Stage Coach RD over Lake Creek in Lane County, Oregon. It was built in 1960, so it is 65 years old, older than the Oregon average of 49.9 years.

The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 5 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.

It carries about 382 vehicles a day, roughly 10% of them trucks, projected to reach 437 by 2025. The structure is 264 ft (80.5 m) long and 31 ft wide. If it were closed, the detour would be 29.2 mi (47 km).

CarriesStage Coach RD
CrossesLake Creek
Location002 E Swisshome
RouteCounty Highway C5020
StateOregon
Coordinates44.05664, -123.79474
Functional classRural Minor Collector

Condition and inspection

Fair

The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.

ComponentRatingMeaning
Deck6 SatisfactoryStructural elements show some minor deterioration.
Superstructure6 SatisfactoryStructural elements show some minor deterioration.
Substructure5 FairAll primary structural elements are sound but may have minor section loss, cracking, spalling or scour.
Channel and channel protection8 Very GoodNo problems noted.
Last inspectionAugust 2023
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourFoundations stable; scour within limits of footing or piles
Structural evaluation5: Somewhat better than minimum adequacy to tolerate being left in place as is
Deck geometry5: Somewhat better than minimum adequacy to tolerate being left in place as is
Waterway adequacy8: Equal to present desirable criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating45.3 US tons
Inventory rating35.1 US tons

Structure

MaterialConcrete Continuous
DeckConcrete, cast-in-place
Main spans3
Design loadHS 20
Structure length264 ft (80.5 m)
Longest span100 ft (30.5 m)
Deck width31 ft (9.4 m)
Roadway width26 ft (8 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic382 (2020)
Projected traffic437 by 2025
Trucks10%
Lanes on structure2
Traffic directionTwo-way traffic
CarriesHighway
CrossesWaterway
Detour if closed29.2 mi (47 km)
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerCounty Highway Agency
Maintained byCounty Highway Agency
Historic statusHistorical significance not determinable at this time
Work proposedNone recorded
Estimated improvement cost—
NavigationNo navigation control on waterway

Frequently asked questions

When was Stage Coach RD over Lake Creek built?

It was built in 1960, making it 65 years old in 2025.

What condition is Stage Coach RD over Lake Creek in?

The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in August 2023.

How much traffic does Stage Coach RD over Lake Creek carry?

About 382 vehicles per day (2020 count), of which roughly 10% are trucks.

How long is Stage Coach RD over Lake Creek?

The structure is 264 ft (80.5 m) long with a longest span of 100 ft (30.5 m) and a deck 31 ft wide.

Who owns Stage Coach RD over Lake Creek?

It is owned by the County Highway Agency.