US101 (hwy 9) over Shangri LA Creek
FairPosted for loadClatsop County, Oregon · 005 MI S Seaside S C Lmts · Structure no. 03080 009 02248
- Built
- 1960
- 65 years old
- Condition
- Fair
- inspected November 2023
- Type
- Channel Beam
- Concrete
- Length
- 76 ft
- 4 main spans
- Daily traffic
- 16,793
- 2022 count
- Owner
- State
- State Highway Agency
About this bridge
US101 (hwy 9) over Shangri LA Creek is a concrete channel beam carrying US101 (hwy 9) over Shangri LA Creek in Clatsop County, Oregon. It was built in 1960, so it is 65 years old, older than the Oregon average of 49.9 years.
The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 5 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. Its operating status is: posted for load restriction.
It carries about 16,793 vehicles a day, roughly 3% of them trucks, projected to reach 16,900 by 2042. The structure is 76 ft (23.2 m) long and 36 ft wide. If it were closed, the detour would be 32.3 mi (52 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 6 Satisfactory | Structural elements show some minor deterioration. |
| Superstructure | 6 Satisfactory | Structural elements show some minor deterioration. |
| Substructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Channel and channel protection | 6 Satisfactory | Structural elements show some minor deterioration. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was US101 (hwy 9) over Shangri LA Creek built?
It was built in 1960, making it 65 years old in 2025.
What condition is US101 (hwy 9) over Shangri LA Creek in?
The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in November 2023.
How much traffic does US101 (hwy 9) over Shangri LA Creek carry?
About 16,793 vehicles per day (2022 count), of which roughly 3% are trucks.
How long is US101 (hwy 9) over Shangri LA Creek?
The structure is 76 ft (23.2 m) long with a longest span of 19 ft (5.8 m) and a deck 36 ft wide.
Who owns US101 (hwy 9) over Shangri LA Creek?
It is owned by the State Highway Agency.