GoodClackamas County, Oregon · 7.2 Miles SE of Molalla O · Structure no. 0000000L1439377
- Built
- 1974
- 51 years old
- Condition
- Good
- inspected February 2023
- Type
- Box Beam or Girders - Single or Spread
- Concrete
- Length
- 162 ft
- 3 main spans
- Daily traffic
- 25
- 2023 count
- Owner
- Federal
- Bureau of Land Management
About this bridge
07 S 03 E 14.00: over Table Rock Fork Molalla is a concrete box beam or girders - single or spread carrying 07 S 03 E 14.00: over Table Rock Fork Molalla in Clackamas County, Oregon. It was built in 1974, so it is 51 years old, older than the Oregon average of 49.9 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 25 vehicles a day, roughly 10% of them trucks, projected to reach 40 by 2043. The structure is 162 ft (49.4 m) long and 31 ft wide. If it were closed, the detour would be 31.1 mi (50 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
| Channel and channel protection | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was 07 S 03 E 14.00: over Table Rock Fork Molalla built?
It was built in 1974, making it 51 years old in 2025.
What condition is 07 S 03 E 14.00: over Table Rock Fork Molalla in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in February 2023.
How much traffic does 07 S 03 E 14.00: over Table Rock Fork Molalla carry?
About 25 vehicles per day (2023 count), of which roughly 10% are trucks.
How long is 07 S 03 E 14.00: over Table Rock Fork Molalla?
The structure is 162 ft (49.4 m) long with a longest span of 104 ft (31.7 m) and a deck 31 ft wide.
Who owns 07 S 03 E 14.00: over Table Rock Fork Molalla?
It is owned by the Bureau of Land Management.