IRR E0990 FAS 2002 over Beaver Creek
GoodCuster County, Oklahoma · .5E of Arapaho · Structure no. 309510000000000
- Built
- 2015
- 10 years old
- Condition
- Good
- inspected September 2024
- Type
- Stringer/Multi-beam or Girder
- Prestressed Concrete
- Length
- 78 ft
- 1 main span
- Daily traffic
- 325
- 2022 count
- Owner
- County
- County Highway Agency
About this bridge
IRR E0990 FAS 2002 over Beaver Creek is a prestressed concrete stringer/multi-beam or girder carrying IRR E0990 FAS 2002 over Beaver Creek in Custer County, Oklahoma. It was built in 2015, so it is 10 years old, younger than the Oklahoma average of 47.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 325 vehicles a day, roughly 15% of them trucks, projected to reach 520 by 2042. The structure is 78 ft (23.8 m) long and 28 ft wide. If it were closed, the detour would be 3.7 mi (6 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 9 Excellent | No problems noted. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 8 Very Good | No problems noted. |
| Channel and channel protection | 8 Very Good | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was IRR E0990 FAS 2002 over Beaver Creek built?
It was built in 2015, making it 10 years old in 2025.
What condition is IRR E0990 FAS 2002 over Beaver Creek in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in September 2024.
How much traffic does IRR E0990 FAS 2002 over Beaver Creek carry?
About 325 vehicles per day (2022 count), of which roughly 15% are trucks.
How long is IRR E0990 FAS 2002 over Beaver Creek?
The structure is 78 ft (23.8 m) long with a longest span of 73 ft (22.3 m) and a deck 28 ft wide.
Who owns IRR E0990 FAS 2002 over Beaver Creek?
It is owned by the County Highway Agency.