US Bridges

Methodist Rd. over I-40 under

Good

Canadian County, Oklahoma · 0.5 MI E Caddo C/L · Structure no. 151380000000000

Built
1960
65 years old
Condition
Good
inspected November 2024
Type
Slab
Concrete Continuous
Length
172 ft
4 main spans
Daily traffic
400
2022 count
Owner
State
State Highway Agency

About this bridge

Methodist Rd. over I-40 under is a concrete continuous slab carrying Methodist Rd. over I-40 under in Canadian County, Oklahoma. It was built in 1960, so it is 65 years old, older than the Oklahoma average of 47.8 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 400 vehicles a day, roughly 15% of them trucks, projected to reach 640 by 2042. The structure is 172 ft (52.4 m) long and 29 ft wide. If it were closed, the detour would be 9.9 mi (16 km).

CarriesMethodist Rd.
CrossesI-40 under
Location0.5 MI E Caddo C/L
RouteCounty Highway N2635
Coordinates35.52293, -98.29765
Functional classRural Major Collector

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck7 GoodSome minor problems.
Superstructure7 GoodSome minor problems.
Substructure8 Very GoodNo problems noted.
Last inspectionNovember 2024
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourBridge not over waterway
Structural evaluation6: Equal to present minimum criteria
Deck geometry5: Somewhat better than minimum adequacy to tolerate being left in place as is
Approach roadway alignment5: Somewhat better than minimum adequacy to tolerate being left in place as is
Operating rating41 US tons
Inventory rating24 US tons

Structure

Structure typeSlab
MaterialConcrete Continuous
DeckConcrete, cast-in-place
Main spans4
Design loadH 15
Structure length172 ft (52.4 m)
Longest span55 ft (16.8 m)
Deck width29 ft (8.8 m)
Roadway width24 ft (7.3 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic400 (2022)
Projected traffic640 by 2042
Trucks15%
Lanes on structure2
Traffic directionTwo-way traffic
CarriesHighway
CrossesHighway
Detour if closed9.9 mi (16 km)
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerState Highway Agency
Maintained byState Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedReplacement because of substandard load-carrying capacity or roadway geometry
Estimated improvement cost$1.9 million
NavigationNot applicable (no waterway)

Frequently asked questions

When was Methodist Rd. over I-40 under built?

It was built in 1960, making it 65 years old in 2025.

What condition is Methodist Rd. over I-40 under in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in November 2024.

How much traffic does Methodist Rd. over I-40 under carry?

About 400 vehicles per day (2022 count), of which roughly 15% are trucks.

How long is Methodist Rd. over I-40 under?

The structure is 172 ft (52.4 m) long with a longest span of 55 ft (16.8 m) and a deck 29 ft wide.

Who owns Methodist Rd. over I-40 under?

It is owned by the State Highway Agency.