US Bridges

E 20th Street over Goettge Run

Good

Tuscarawas County, Ohio · 0.25 MI E of Wooster Av. · Structure no. 7960191

Built
2024
1 years old
Condition
Good
inspected December 2024
Type
Culvert
Concrete
Length
22 ft
1 main span
Daily traffic
190
2022 count
Owner
City
City or Municipal Highway Agency

About this bridge

E 20th Street over Goettge Run is a concrete culvert carrying E 20th Street over Goettge Run in Tuscarawas County, Ohio. It was built in 2024, so it is 1 years old, younger than the Ohio average of 47.3 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 9 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 190 vehicles a day, roughly 3% of them trucks, projected to reach 230 by 2042. The structure is 22 ft (6.8 m) long and 75 ft wide. If it were closed, the detour would be 1.2 mi (2 km).

CarriesE 20th Street
CrossesGoettge Run
Location0.25 MI E of Wooster Av.
RouteCity Street E20ST
StateOhio
Coordinates40.54162, -81.48494
Functional classUrban Local

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Channel and channel protection9 ExcellentNo problems noted.
Culvert9 ExcellentNo problems noted.
Last inspectionDecember 2024
Inspection intervalevery 12 months
Operating statusOpen, no restriction
ScourFoundations stable; scour above top of footing
Structural evaluation9: Superior to present desirable criteria
Deck geometry7: Better than present minimum criteria
Waterway adequacy7: Better than present minimum criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating54.7 US tons
Inventory rating42.1 US tons

Structure

Structure typeCulvert
MaterialConcrete
DeckNot applicable
Main spans1
Design loadHL 93
Structure length22 ft (6.8 m)
Longest span22 ft (6.8 m)
Deck width75 ft (23 m)
Roadway width35 ft (10.7 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic190 (2022)
Projected traffic230 by 2042
Trucks3%
Lanes on structure2
Traffic directionTwo-way traffic
CarriesHighway
CrossesWaterway
Detour if closed1.2 mi (2 km)
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerCity or Municipal Highway Agency
Maintained byCity or Municipal Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedNone recorded
Estimated improvement cost—
NavigationNo navigation control on waterway

Frequently asked questions

When was E 20th Street over Goettge Run built?

It was built in 2024, making it 1 years old in 2025.

What condition is E 20th Street over Goettge Run in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in December 2024.

How much traffic does E 20th Street over Goettge Run carry?

About 190 vehicles per day (2022 count), of which roughly 3% are trucks.

How long is E 20th Street over Goettge Run?

The structure is 22 ft (6.8 m) long with a longest span of 22 ft (6.8 m) and a deck 75 ft wide.

Who owns E 20th Street over Goettge Run?

It is owned by the City or Municipal Highway Agency.