S Main ST CO RD 50 over Nimisila Creek
GoodSummit County, Ohio · 750 Ft N of Nimisila RD · Structure no. 7738366
- Built
- 1991
- 34 years old, rebuilt 2023
- Condition
- Good
- inspected February 2024
- Type
- Box Beam or Girders - Multiple
- Prestressed Concrete
- Length
- 51 ft
- 1 main span
- Daily traffic
- 5,890
- 2022 count
- Owner
- County
- County Highway Agency
About this bridge
S Main ST CO RD 50 over Nimisila Creek is a prestressed concrete box beam or girders - multiple carrying S Main ST CO RD 50 over Nimisila Creek in Summit County, Ohio. It was built in 1991 and reconstructed in 2023, so it is 34 years old, younger than the Ohio average of 47.3 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 8 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 5,890 vehicles a day, roughly 1% of them trucks, projected to reach 6,180 by 2042. The structure is 51 ft (15.6 m) long and 38 ft wide. If it were closed, the detour would be 6.8 mi (11 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 9 Excellent | No problems noted. |
| Superstructure | 9 Excellent | No problems noted. |
| Substructure | 8 Very Good | No problems noted. |
| Channel and channel protection | 8 Very Good | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was S Main ST CO RD 50 over Nimisila Creek built?
It was built in 1991, making it 34 years old in 2025. It was reconstructed in 2023.
What condition is S Main ST CO RD 50 over Nimisila Creek in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in February 2024.
How much traffic does S Main ST CO RD 50 over Nimisila Creek carry?
About 5,890 vehicles per day (2022 count), of which roughly 1% are trucks.
How long is S Main ST CO RD 50 over Nimisila Creek?
The structure is 51 ft (15.6 m) long with a longest span of 48 ft (14.6 m) and a deck 38 ft wide.
Who owns S Main ST CO RD 50 over Nimisila Creek?
It is owned by the County Highway Agency.