Knox County, Ohio · 0.1 MI W of Hill RD · Structure no. 4235844

Built
2022
3 years old
Condition
Good
inspected April 2024
Type
Box Beam or Girders - Multiple
Prestressed Concrete
Length
43 ft
1 main span
Daily traffic
330
2015 count
Owner
County
County Highway Agency

About this bridge

Caves Road over Barney Run is a prestressed concrete box beam or girders - multiple carrying Caves Road over Barney Run in Knox County, Ohio. It was built in 2022, so it is 3 years old, younger than the Ohio average of 47.3 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 9 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 330 vehicles a day, roughly 8% of them trucks, projected to reach 444 by 2042. The structure is 43 ft (13.1 m) long and 24 ft wide. If it were closed, the detour would be 3.7 mi (6 km).

CarriesCaves Road
CrossesBarney Run
Location0.1 MI W of Hill RD
RouteCounty Highway 226
StateOhio
Coordinates40.38087, -82.31411
Functional classRural Local

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck9 ExcellentNo problems noted.
Superstructure9 ExcellentNo problems noted.
Substructure9 ExcellentNo problems noted.
Channel and channel protection8 Very GoodNo problems noted.
Last inspectionApril 2024
Inspection intervalevery 12 months
Operating statusOpen, no restriction
ScourFoundations stable; scour within limits of footing or piles
Structural evaluation9: Superior to present desirable criteria
Deck geometry5: Somewhat better than minimum adequacy to tolerate being left in place as is
Waterway adequacy8: Equal to present desirable criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating58.2 US tons
Inventory rating45 US tons

Structure

MaterialPrestressed Concrete
DeckNot applicable
Main spans1
Design loadHL 93
Structure length43 ft (13.1 m)
Longest span39 ft (11.9 m)
Deck width24 ft (7.3 m)
Roadway width24 ft (7.3 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic330 (2015)
Projected traffic444 by 2042
Trucks8%
Lanes on structure2
Traffic directionTwo-way traffic
CarriesHighway
CrossesWaterway
Detour if closed3.7 mi (6 km)
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerCounty Highway Agency
Maintained byCounty Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedNone recorded
Estimated improvement cost—
NavigationNo navigation control on waterway

Frequently asked questions

When was Caves Road over Barney Run built?

It was built in 2022, making it 3 years old in 2025.

What condition is Caves Road over Barney Run in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in April 2024.

How much traffic does Caves Road over Barney Run carry?

About 330 vehicles per day (2015 count), of which roughly 8% are trucks.

How long is Caves Road over Barney Run?

The structure is 43 ft (13.1 m) long with a longest span of 39 ft (11.9 m) and a deck 24 ft wide.

Who owns Caves Road over Barney Run?

It is owned by the County Highway Agency.