County RD 51 over German Twp RD 159
FairHarrison County, Ohio · At Int of CR 51&TWP 159 · Structure no. 3431541
- Built
- 1960
- 65 years old
- Condition
- Fair
- inspected October 2024
- Type
- Stringer/Multi-beam or Girder
- Steel
- Length
- 29 ft
- 1 main span
- Daily traffic
- 235
- 2015 count
- Owner
- County
- County Highway Agency
About this bridge
County RD 51 over German Twp RD 159 is a steel stringer/multi-beam or girder carrying County RD 51 over German Twp RD 159 in Harrison County, Ohio. It was built in 1960, so it is 65 years old, older than the Ohio average of 47.3 years.
The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 5 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
It carries about 235 vehicles a day, roughly 7% of them trucks, projected to reach 326 by 2035. The structure is 29 ft (8.8 m) long and 27 ft wide. If it were closed, the detour would be 3.1 mi (5 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Superstructure | 6 Satisfactory | Structural elements show some minor deterioration. |
| Substructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was County RD 51 over German Twp RD 159 built?
It was built in 1960, making it 65 years old in 2025.
What condition is County RD 51 over German Twp RD 159 in?
The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in October 2024.
How much traffic does County RD 51 over German Twp RD 159 carry?
About 235 vehicles per day (2015 count), of which roughly 7% are trucks.
How long is County RD 51 over German Twp RD 159?
The structure is 29 ft (8.8 m) long with a longest span of 27 ft (8.2 m) and a deck 27 ft wide.
Who owns County RD 51 over German Twp RD 159?
It is owned by the County Highway Agency.