Por Twp RD 19 over Isiac Insley
GoodHancock County, Ohio · 0.17 MI W CR 139 · Structure no. 3231100
- Built
- 1993
- 32 years old
- Condition
- Good
- inspected March 2023
- Type
- Box Beam or Girders - Multiple
- Prestressed Concrete
- Length
- 40 ft
- 1 main span
- Daily traffic
- 324
- 2015 count
- Owner
- County
- County Highway Agency
About this bridge
Por Twp RD 19 over Isiac Insley is a prestressed concrete box beam or girders - multiple carrying Por Twp RD 19 over Isiac Insley in Hancock County, Ohio. It was built in 1993, so it is 32 years old, younger than the Ohio average of 47.3 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 8 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 324 vehicles a day, roughly 7% of them trucks, projected to reach 450 by 2035. The structure is 40 ft (12.2 m) long and 24 ft wide. If it were closed, the detour would be 3.1 mi (5 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 8 Very Good | No problems noted. |
| Superstructure | 8 Very Good | No problems noted. |
| Substructure | 8 Very Good | No problems noted. |
| Channel and channel protection | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Por Twp RD 19 over Isiac Insley built?
It was built in 1993, making it 32 years old in 2025.
What condition is Por Twp RD 19 over Isiac Insley in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in March 2023.
How much traffic does Por Twp RD 19 over Isiac Insley carry?
About 324 vehicles per day (2015 count), of which roughly 7% are trucks.
How long is Por Twp RD 19 over Isiac Insley?
The structure is 40 ft (12.2 m) long with a longest span of 39 ft (11.9 m) and a deck 24 ft wide.
Who owns Por Twp RD 19 over Isiac Insley?
It is owned by the County Highway Agency.