Medallion Drive over Mill Creek
FairHamilton County, Ohio · 0.5 Miles of Gmr · Structure no. 3165094
- Built
- 1997
- 28 years old
- Condition
- Fair
- inspected April 2024
- Type
- Box Beam or Girders - Multiple
- Prestressed Concrete
- Length
- 165 ft
- 3 main spans
- Daily traffic
- 100
- 1999 count
- Owner
- City
- City or Municipal Highway Agency
About this bridge
Medallion Drive over Mill Creek is a prestressed concrete box beam or girders - multiple carrying Medallion Drive over Mill Creek in Hamilton County, Ohio. It was built in 1997, so it is 28 years old, younger than the Ohio average of 47.3 years.
The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 5 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
It carries about 100 vehicles a day, roughly 10% of them trucks, projected to reach 139 by 2019. The structure is 165 ft (50.3 m) long and 34 ft wide. If it were closed, the detour would be 3.1 mi (5 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 6 Satisfactory | Structural elements show some minor deterioration. |
| Superstructure | 6 Satisfactory | Structural elements show some minor deterioration. |
| Substructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Channel and channel protection | 8 Very Good | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Medallion Drive over Mill Creek built?
It was built in 1997, making it 28 years old in 2025.
What condition is Medallion Drive over Mill Creek in?
The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in April 2024.
How much traffic does Medallion Drive over Mill Creek carry?
About 100 vehicles per day (1999 count), of which roughly 10% are trucks.
How long is Medallion Drive over Mill Creek?
The structure is 165 ft (50.3 m) long with a longest span of 55 ft (16.8 m) and a deck 34 ft wide.
Who owns Medallion Drive over Mill Creek?
It is owned by the City or Municipal Highway Agency.