PoorHamilton County, Ohio · 2.3 MI S of SR 126 · Structure no. 3110656
- Built
- 1965
- 60 years old
- Condition
- Poor
- inspected July 2024
- Type
- Stringer/Multi-beam or Girder
- Steel Continuous
- Length
- 2,418 ft
- 23 main spans
- Daily traffic
- 67,075
- 2015 count
- Owner
- State
- State Highway Agency
About this bridge
NB Ir 75 over Mill Cr;benson St;nsrr;s is a steel continuous stringer/multi-beam or girder carrying NB Ir 75 over Mill Cr;benson St;nsrr;s in Hamilton County, Ohio. It was built in 1965, so it is 60 years old, older than the Ohio average of 47.3 years.
The most recent inspection reported to the Federal Highway Administration rates it in poor condition with a lowest component rating of 4 out of 9. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions.
It carries about 67,075 vehicles a day, roughly 16% of them trucks, projected to reach 93,100 by 2035. The structure is 2,418 ft (737 m) long and 54 ft wide. If it were closed, the detour would be 3.1 mi (5 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 6 Satisfactory | Structural elements show some minor deterioration. |
| Superstructure | 4 Poor | Advanced section loss, deterioration, spalling or scour. |
| Substructure | 7 Good | Some minor problems. |
| Channel and channel protection | 6 Satisfactory | Structural elements show some minor deterioration. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was NB Ir 75 over Mill Cr;benson St;nsrr;s built?
It was built in 1965, making it 60 years old in 2025.
What condition is NB Ir 75 over Mill Cr;benson St;nsrr;s in?
The National Bridge Inventory rates it in poor condition. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions. The last reported inspection was in July 2024.
How much traffic does NB Ir 75 over Mill Cr;benson St;nsrr;s carry?
About 67,075 vehicles per day (2015 count), of which roughly 16% are trucks.
How long is NB Ir 75 over Mill Cr;benson St;nsrr;s?
The structure is 2,418 ft (737 m) long with a longest span of 156 ft (47.5 m) and a deck 54 ft wide.
Who owns NB Ir 75 over Mill Cr;benson St;nsrr;s?
It is owned by the State Highway Agency.