NB Ir 675 over Quarry Rr;priv Dr(qy Rd)
GoodGreene County, Ohio · .2 MI S of SR 235 · Structure no. 2904187
- Built
- 1974
- 51 years old
- Condition
- Good
- inspected December 2024
- Type
- Stringer/Multi-beam or Girder
- Steel Continuous
- Length
- 268 ft
- 4 main spans
- Daily traffic
- 20,656
- 2015 count
- Owner
- State
- State Highway Agency
About this bridge
NB Ir 675 over Quarry Rr;priv Dr(qy Rd) is a steel continuous stringer/multi-beam or girder carrying NB Ir 675 over Quarry Rr;priv Dr(qy Rd) in Greene County, Ohio. It was built in 1974, so it is 51 years old, older than the Ohio average of 47.3 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 20,656 vehicles a day, roughly 17% of them trucks, projected to reach 28,671 by 2035. The structure is 268 ft (81.7 m) long and 44 ft wide. If it were closed, the detour would be 1.9 mi (3 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was NB Ir 675 over Quarry Rr;priv Dr(qy Rd) built?
It was built in 1974, making it 51 years old in 2025.
What condition is NB Ir 675 over Quarry Rr;priv Dr(qy Rd) in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in December 2024.
How much traffic does NB Ir 675 over Quarry Rr;priv Dr(qy Rd) carry?
About 20,656 vehicles per day (2015 count), of which roughly 17% are trucks.
How long is NB Ir 675 over Quarry Rr;priv Dr(qy Rd)?
The structure is 268 ft (81.7 m) long with a longest span of 78 ft (23.8 m) and a deck 44 ft wide.
Who owns NB Ir 675 over Quarry Rr;priv Dr(qy Rd)?
It is owned by the State Highway Agency.