US Bridges

County RD 12 over Raccoon Creek

Good

Gallia County, Ohio · 20E.OF Maple Grove Rd. · Structure no. 2741822

Built
2007
18 years old
Condition
Good
inspected August 2024
Type
Stringer/Multi-beam or Girder
Prestressed Concrete Continuous
Length
244 ft
3 main spans
Daily traffic
175
2015 count
Owner
County
County Highway Agency

About this bridge

County RD 12 over Raccoon Creek is a prestressed concrete continuous stringer/multi-beam or girder carrying County RD 12 over Raccoon Creek in Gallia County, Ohio. It was built in 2007, so it is 18 years old, younger than the Ohio average of 47.3 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 8 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 175 vehicles a day, roughly 7% of them trucks, projected to reach 243 by 2035. The structure is 244 ft (74.4 m) long and 28 ft wide. If it were closed, the detour would be 6.8 mi (11 km).

CarriesCounty RD 12
CrossesRaccoon Creek
Location20E.OF Maple Grove Rd.
RouteCounty Highway C0012
StateOhio
Coordinates38.82511, -82.36917
Functional classRural Local

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck8 Very GoodNo problems noted.
Superstructure8 Very GoodNo problems noted.
Substructure8 Very GoodNo problems noted.
Channel and channel protection7 GoodSome minor problems.
Last inspectionAugust 2024
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourFoundations stable; scour above top of footing
Structural evaluation5: Somewhat better than minimum adequacy to tolerate being left in place as is
Deck geometry6: Equal to present minimum criteria
Waterway adequacy8: Equal to present desirable criteria
Approach roadway alignment7: Better than present minimum criteria
Operating rating43.5 US tons
Inventory rating21.1 US tons

Structure

MaterialPrestressed Concrete Continuous
DeckConcrete, cast-in-place
Main spans3
Design loadHL 93
Structure length244 ft (74.4 m)
Longest span80 ft (24.4 m)
Deck width28 ft (8.5 m)
Roadway width28 ft (8.5 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic175 (2015)
Projected traffic243 by 2035
Trucks7%
Lanes on structure2
Traffic directionTwo-way traffic
CarriesHighway
CrossesWaterway
Detour if closed6.8 mi (11 km)
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerCounty Highway Agency
Maintained byCounty Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedNone recorded
Estimated improvement cost—
NavigationNo navigation control on waterway

Frequently asked questions

When was County RD 12 over Raccoon Creek built?

It was built in 2007, making it 18 years old in 2025.

What condition is County RD 12 over Raccoon Creek in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in August 2024.

How much traffic does County RD 12 over Raccoon Creek carry?

About 175 vehicles per day (2015 count), of which roughly 7% are trucks.

How long is County RD 12 over Raccoon Creek?

The structure is 244 ft (74.4 m) long with a longest span of 80 ft (24.4 m) and a deck 28 ft wide.

Who owns County RD 12 over Raccoon Creek?

It is owned by the County Highway Agency.