US Bridges

MAD-29 Clearport R over Clearcr(clearport RD SW

Good

Fairfield County, Ohio · 0.1 MI N of Julian RD SW · Structure no. 2339285

Built
1987
38 years old
Condition
Good
inspected November 2023
Type
Slab
Concrete Continuous
Length
117 ft
3 main spans
Daily traffic
38
2015 count
Owner
County
County Highway Agency

About this bridge

MAD-29 Clearport R over Clearcr(clearport RD SW is a concrete continuous slab carrying MAD-29 Clearport R over Clearcr(clearport RD SW in Fairfield County, Ohio. It was built in 1987, so it is 38 years old, younger than the Ohio average of 47.3 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 8 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 38 vehicles a day, roughly 8% of them trucks, projected to reach 53 by 2035. The structure is 117 ft (35.7 m) long and 28 ft wide. If it were closed, the detour would be 5 mi (8 km).

CarriesMAD-29 Clearport R
CrossesClearcr(clearport RD SW
Location0.1 MI N of Julian RD SW
RouteCounty Highway C0024
StateOhio
Coordinates39.61845, -82.68082
Functional classRural Local

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck8 Very GoodNo problems noted.
Superstructure8 Very GoodNo problems noted.
Substructure8 Very GoodNo problems noted.
Channel and channel protection8 Very GoodNo problems noted.
Last inspectionNovember 2023
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourFoundations stable; scour above top of footing
Structural evaluation8: Equal to present desirable criteria
Deck geometry7: Better than present minimum criteria
Waterway adequacy7: Better than present minimum criteria
Approach roadway alignment7: Better than present minimum criteria
Operating rating68.6 US tons
Inventory rating52.9 US tons

Structure

Structure typeSlab
MaterialConcrete Continuous
DeckConcrete, cast-in-place
Main spans3
Design loadHS 20 + Mod
Structure length117 ft (35.7 m)
Longest span45 ft (13.7 m)
Deck width28 ft (8.5 m)
Roadway width28 ft (8.5 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic38 (2015)
Projected traffic53 by 2035
Trucks8%
Lanes on structure2
Traffic directionTwo-way traffic
CarriesHighway
CrossesWaterway
Detour if closed5 mi (8 km)
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerCounty Highway Agency
Maintained byCounty Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedNone recorded
Estimated improvement cost—
NavigationNo navigation control on waterway

Frequently asked questions

When was MAD-29 Clearport R over Clearcr(clearport RD SW built?

It was built in 1987, making it 38 years old in 2025.

What condition is MAD-29 Clearport R over Clearcr(clearport RD SW in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in November 2023.

How much traffic does MAD-29 Clearport R over Clearcr(clearport RD SW carry?

About 38 vehicles per day (2015 count), of which roughly 8% are trucks.

How long is MAD-29 Clearport R over Clearcr(clearport RD SW?

The structure is 117 ft (35.7 m) long with a longest span of 45 ft (13.7 m) and a deck 28 ft wide.

Who owns MAD-29 Clearport R over Clearcr(clearport RD SW?

It is owned by the County Highway Agency.