US Bridges

Township Road 65 over Sand Fork

Fair

Coshocton County, Ohio · 0.25MI N Int CR4 · Structure no. 1634364

Built
2007
18 years old
Condition
Fair
inspected March 2024
Type
Box Beam or Girders - Multiple
Prestressed Concrete
Length
28 ft
1 main span
Daily traffic
209
2015 count
Owner
County
County Highway Agency

About this bridge

Township Road 65 over Sand Fork is a prestressed concrete box beam or girders - multiple carrying Township Road 65 over Sand Fork in Coshocton County, Ohio. It was built in 2007, so it is 18 years old, younger than the Ohio average of 47.3 years.

The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 6 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.

It carries about 209 vehicles a day, roughly 7% of them trucks, projected to reach 290 by 2035. The structure is 28 ft (8.5 m) long and 20 ft wide. If it were closed, the detour would be 3.7 mi (6 km).

CarriesTownship Road 65
CrossesSand Fork
Location0.25MI N Int CR4
RouteCounty Highway T0065
StateOhio
Coordinates40.21944, -82.0098
Functional classRural Local

Condition and inspection

Fair

The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.

ComponentRatingMeaning
Deck7 GoodSome minor problems.
Superstructure7 GoodSome minor problems.
Substructure6 SatisfactoryStructural elements show some minor deterioration.
Channel and channel protection7 GoodSome minor problems.
Last inspectionMarch 2024
Inspection intervalevery 12 months
Operating statusOpen, no restriction
ScourFoundations stable; scour within limits of footing or piles
Structural evaluation6: Equal to present minimum criteria
Deck geometry4: Meets minimum tolerable limits to be left in place as is
Waterway adequacy7: Better than present minimum criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating68.9 US tons
Inventory rating53.2 US tons

Structure

MaterialPrestressed Concrete
DeckConcrete, cast-in-place
Main spans1
Design loadHS 20 + Mod
Structure length28 ft (8.5 m)
Longest span25 ft (7.6 m)
Deck width20 ft (6.1 m)
Roadway width20 ft (6.1 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic209 (2015)
Projected traffic290 by 2035
Trucks7%
Lanes on structure2
Traffic directionTwo-way traffic
CarriesHighway
CrossesWaterway
Detour if closed3.7 mi (6 km)
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerCounty Highway Agency
Maintained byCounty Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedNone recorded
Estimated improvement cost—
NavigationNo navigation control on waterway

Frequently asked questions

When was Township Road 65 over Sand Fork built?

It was built in 2007, making it 18 years old in 2025.

What condition is Township Road 65 over Sand Fork in?

The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in March 2024.

How much traffic does Township Road 65 over Sand Fork carry?

About 209 vehicles per day (2015 count), of which roughly 7% are trucks.

How long is Township Road 65 over Sand Fork?

The structure is 28 ft (8.5 m) long with a longest span of 25 ft (7.6 m) and a deck 20 ft wide.

Who owns Township Road 65 over Sand Fork?

It is owned by the County Highway Agency.